SSIS Successfully Completes Third Decline Portal Tunnel at SASOL's Shondoni Mine

SSIS successfully completed the installation of a 60 m long decline tunnel at SASOL's Shondoni Mine working with Aveng Grinaker-LTA Mining.

The installation process was well planned and monitored by Aveng Grinaker-LTA Mining with safety their number one priority.  The structure was pre-assembled in sections next to the decline followed by lifting each section in place using a crane.  It took only 5 days for the entire 60m long structure to be installed in the decline.  The structure is to be backfilled next.

 

Lifting two Super•Cor Rings into place.

     
 

Each ring was bolted to the previous ring under SSIS supervision.

     
  The completed 60m long tunnel on a 12° decline angle
     
 

Applying supplementary LiquidRubber corrosion coating

     
 

Completed and coated Super•Cor decline tunnel

Project-at-a-glance

Project Location: SASOL, Shondoni Mine
Location: Secunda, Mpumalanga
Type of Product: Super.Cor
Dimensions: 7.933 Span x 4.046m Rise
Installation Time (start to finish): 22 working days

 